Mount Kisco Heads Into a Second Holiday Season Without the Preston Way Bridge

November 12, 2026

Nick Bueti found out about the Preston Way Bridge from a robocall. It came just before the New York State Department of Transportation closed the span on December 3, 2025. Bueti co-owns Mount Kisco Wines & Spirits on North Bedford Road, and the bridge is visible from his store. He told The Recorder in March that after more than 30 years in business he could more or less predict his sales. Then the bridge closed.

Almost a year on, the bridge is moving again. NYSDOT approved the redesigned plans on November 4, the village published its bid notice on November 9, and contractors' bids will be opened and read aloud at Village Hall at 11 a.m. on Monday, December 21. The approval is real progress, but the steps it sets in motion run well past this December. The North Bedford Road side of the tracks is now planning around a second closed holiday season, and very likely a third.

The calendar since the closure

The 72-year-old bridge links North Bedford Road, which is Route 117, with Kisco Avenue over Metro-North's Harlem Line tracks. NYSDOT closed it because of severe structural deterioration and traffic safety concerns after lowering its weight limits, as Halston Media reported. The calendar since then, taken from the village's own project updates:

  1. February 18, 2026. The village and the MTA sign the Master Entry Permit Agreement, which NYSDOT required before bidding could start.
  2. March and April 2026. Crews begin clearing the four embankments around the bridge in March, under a March 31 deadline set by state limits on cutting trees between April 1 and October 31, which protect endangered Indiana bats. The village's April 6 update reports the embankments cleared.
  3. May 18, 2026. This was the bid date NYSDOT had given. That same month the department asked for revisions to the design, so the bid was delayed.
  4. June 2026. The village submits the redesigned abutments.
  5. November 4, 2026. NYSDOT approves the redesign.
  6. December 21, 2026. Bids are opened at Village Hall.

The Recorder put the cost of the redesign request at nearly six months. In March, Village Manager Ed Brancati said bidding would run until about May 18, construction would start by August, and the work would take 12 to 14 months. On that schedule, the new bridge would have opened sometime in the second half of 2027. Bids now open in late December, and officials say construction will take at least a year once the old span is demolished. Trustee Heather Bryant has put the build at 12 to 18 months from the start of site work.

Why the bid opening is not the finish line

Opening the bids answers the question the village has been asking since January, which is what the bridge will actually cost. The working estimate is $8.6 million, and it dates from almost three years ago. The Recorder reported that the real number is almost certain to be higher because of inflation, tariffs and other factors.

Here is what the village has to work with so far:

Funding piece Amount Status as of November 2026
State grant $5 million Secured
Village borrowing $3.6 million Already borrowed
Additional state funding Not disclosed Confirmed by the state, amount pending
MTA force account Railroad support labor such as flaggers and inspectors Paid by the MTA, not the village

The board might not award a contract on December 21. A board meeting is scheduled for that evening, and a special meeting can also be called. Before construction, the village's consulting engineers review the plans of the lowest responsible bidder. If the bids come in above the money on hand, Trustee Tom Luzio has said officials will take the real number to state representatives and ask for more.

Each of those steps comes before demolition, and the year or more of construction starts only after demolition. In October, before the design was approved, Mayor J. Michael Cindrich told The Recorder that a new bridge was increasingly unlikely to open before 2028. The schedule laid out above points the same way.

One stretch of road carries the detour

While the bridge is closed, traffic that used to cross the tracks at Preston Way goes around through Main Street and onto North Bedford Road. Mount Kisco Chamber of Commerce President Ed Reilly has named the main chokepoint. It runs from the Route 117 and Route 133 intersection to the Maple Avenue and Kisco Avenue crossing. He told The Recorder in March that the backups come at certain times in the morning and again in the evening, and that between about 10 a.m. and the end of the school day traffic is normal. He also said the southern part of the village has seen little effect.

The chamber has passed along alternate routes for people driving in. Drivers used to coming south on the Saw Mill River Parkway can switch to Interstate 684. Drivers coming from the south can get off at Roaring Brook Road in Chappaqua and head north. In January, Brancati said NYSDOT had made its first adjustments to signals along the detour and installed cameras to gather data before making more temporary changes, according to Halston Media.

The time adds up. A resident told The Examiner in February that driving to Fox Lane High School for drop-off now adds at least 20 to 25 minutes to every round trip. NYSDOT closed the bridge to pedestrians as well as cars. At a Village Board meeting in March, a resident said people who used to cross on foot now walk around by Main Street and Northwest Road. In May, the village formally asked NYSDOT to allow pedestrians across the bridge.

The cost lands on North Bedford Road

Because the detour feeds North Bedford Road, the businesses along it have reported the biggest effects. The figures below are owners' own estimates, given to The Recorder and The Mt. Kisco-Bedford Times at different points in the year:

Business What the owner reported When
Mount Kisco Wines & Spirits Sales down 15% to 20% March 2026
Mount Kisco Wines & Spirits Sales down 25% since the closure September 2026
Mount Kisco Chevrolet Sales off as much as 40%, not all of it from the bridge September 2026
L'Anjou Patisserie Francaise "Not destructive," though a reopened bridge would help March 2026
Mount Kisco Truck & Auto Parts Some customers going to competitors who can deliver faster from across the bridge July 2026

The auto parts account comes from co-owner Pete Finkelstein, who described it to The Mt. Kisco-Bedford Times in July. The Mount Kisco Chevrolet figure came from managing partner Oscar de la Puente, whose dealership sits on the North Bedford Road side of the bridge. He was careful to say the bridge is not the only cause. Patrice Yvon, owner and chef at L'Anjou, said in March that last winter's cold and snow also hurt sales, which makes the bridge's share hard to separate out. Mayor Cindrich also received a letter from the franchise owner of the Burger King on North Bedford Road, which has been there since 1977, asking for relief.

Shoppers have adjusted as well. Leigh Hodgson owns The Hamlet, a British goods shop on South Moger Avenue. She told The Recorder that as a village resident she now stays away from the Target on North Bedford Road and often has her groceries delivered.

New business is still coming to the road. Shake Shack opened its first northern Westchester location at 176 North Bedford Road on September 16, with opening-day sandwich sales benefiting Feeding Westchester, as The Recorder reported. General manager Brandi Miles said it would be open every day, from 10 a.m. to 11 p.m. on weekdays and until midnight on Fridays and Saturdays.

How the chamber is spending the second season

At a September 25 forum at the Mount Kisco Public Library, the chamber and the village's Economic Development Council drew up an action plan. It includes working with the village on the downtown bottleneck, looking into a temporary bridge, and keeping pressure on NYSDOT. Chamber Co-executive Director Beth Vetare-Civitello said much of the SeptemberFest proceeds would go to advertising and publicity promoting village businesses through the holiday shopping season. Mayor Cindrich gave the reason at the same forum.

"The Mount Kisco economy is suffering and we're looking at the possibility of going through not only the 2026 holiday season but possibly the 2027 holiday season."

The chamber's calendar lists three things between now and the end of the year:

  • Shop Small Saturday, running November 1 through December 31 under the chamber's "Shop Local...Shop Kisco!" message.
  • Holiday Tree Lighting Ceremony, Friday, December 4, 6 to 7 p.m., on the Village Green in front of the library at 104 East Main Street.
  • HOLIDAY'FEST! and the MKCC Cookie Crawl, Saturday, December 12, noon to 4 p.m., on the Promenade and South Moger Avenue near the gazebo and the train station.

The tree lighting falls the day after the first anniversary of the closure. HOLIDAY'FEST! runs on a Saturday afternoon, outside the weekday rush Reilly described, and nine days before the bids are opened at Village Hall.

Many of the homes I work with in Mount Kisco sit on one side of the tracks or the other, and this year the bridge has shaped how people get to work, school and the train. If you are thinking about what the Preston Way timeline means for a home near North Bedford Road or Kisco Avenue, Lindsay Matthews can walk you through how the closure is affecting that part of the village right now. Get a Free Home Valuation and we can start there.